WORK INTENSIFIES ON CULVERTS IN MC KINNON’S WATERSHED

Published

on

Report filed by Cherilyn Beazer – News Reporter

Work has intensified in the lower end of the McKinnon’s waterway which meanders from the Woods Pond through Fort Road and Yorks.

Thirteen culverts are being built and are at different stages of construction. Culverts one and two were completed earlier this year with a target date of April 2022 for completion of the other 11.

Cherilyn Beazer reports on the work being carried out.